I To start working
with LEPSE, firstly you need to determine the values of model
element's parameters. All variables are presented in basic
per-units (p.u.b.) of measurement - so you need to choose 2
basic values: basic power
and basic voltage
, for example: 1000 MVA and 340 kV.
The next stage is to calculate values of parameters in p.u.b. with the use of well known formulas. Here are examples of some parameter's conversion from per-units or named units (Om, MVA, MW etc) to basic per-units. An example for all parameter's calculations is presented in Excel-file "Conversion".
- reactivity of
synchronous generator (xd,
xq, x'd, etc);
- reactivity of
transformer;
- reactivity of
power transmission line;
- reactivity of external power
system;
- reactivity of shunt
reactor;
- reactive
conductivity of load.
All the active resistances in basic per-units can be calculated in th same way, except resistances of field and damper windings, which can be calculeted dy the formulas below.

It should be noted that in most cases there is a necessity to equivalent power system grid to simplify dynamic model. In these case several power transmission lines, transformers, generators and loads can be equivalented into one. It is taken into account in "Conversion" file.
II Every scheme needs
infinite bus - "big" equivalent generator. It's parameters
can be easily calculated using the same method as for a
conventional generator. The defining initial parameter for this
calculation is the total short-circuit power
, which defines the total power of external system and
is determined by the following formula:
,
where Isc - nominal short-circuit cut-off current; Uline - nominal phase-to-phase voltage of the line. If there are several lines of communication with the external power system, the short-circuit power is determined by summing the calculated Ssc value for each line.
Then the infinite bus is equivalent to the number of generators required to provide the total short-circuit power. It is normal, for example, if infinite bus is equivalent to 50 generators of 500 MVA nominal power.
To get quasi-steady-state condition, you need to manually set a dummy load at the infinite power bus connection point so that the power system maintains a balance between generation and consumption. This balance can be easily monitored by the slip value s of the equivalent generator of the external power system - ideally, it must be near zero.
III To investigate
transient processes, certain emergency events are needed. Simple
switching off (on) is specified by three parameters - time of
the element's shutdown (TLineOff, TtOff etc),
duration of shutdown (dTLineOff, dTtOff etc) and the
degree of its shutdown (Koff) . The latter means either
the shutdown of a part of the generation/load, or the shutdown of
one circuit or one transformer of the equivalent power line and
equivalent transformer, respectively. In real power energy systems
the main reason of emergency shutdown is short circuit,
which is simulated by ShortCircuitShunt switching on.
There are 4 main parameters of ShortCircuitShunt: reactive, active
conductivity of short sircuit, time of its start and duration. The
fifth parameter, total conductvity of short circuit, is useful,
when you need to save the same degree of voltage drop duiring short
circuit, varying the ratio between its active and reactive
components. To simulate repeated short circuit, you need another
ShortCircuitShunt model. The second power transmission line
shutdown after its automatic reclosing can be simulated with the
help of TLineOff_1,
dTLineOff_1 and Koff_1 parameters.
IV LEPSE allows to
investigate different means of increasing dynamic stability. The
first of them is the changement of Automatic Voltage
Regulator (AVR) control coefficients in Excitation_Regulator model
as well as setpoints of field forcing, which is realised by
logical_switch
implementation in AVR model. The second one is series or parallel
electrical breaking, Electrical_Braking and
Electrical_Braking_Parallel
accordingly, which efficiency depends on their active resistanse
value. The third mean is
fast turbine valving control or turbine fast
valving (defined by T_regOff, T_regOn, Aimp, Timp, dTimp values) as well as
automatic speed controller (ASC) parameters changement
(Sigma and TauCup).
The fourth mean is automatic reclosing, which was mentioned
before. Finally, the fifth way to increase dynamic stability is
generation or load reduction or disabling.